Sitholeni Water Treatment Works

Project Details:

Project Description:
Cluster 6 Water Backlog – Sitholeni Treatment Works and Rising Main

Contract No:
21/2015/MD (TN)

Category:
Municipal Infrastructure

Client:
Chris Hani District Municipality

Consultant:
Sinakho Consulting

Value:
R113M

Completed:
December 2017

Project Overview / Summary:

B 545

Contracts Manager:
J Terblans

Construction Manager:
J Botha

 

The project would comprise the following:

  • Abstraction from the Mbashe River
  • Sitholeni Water Treatment Works with a capacity of 1.3 megalitres/day
  • 2km of 200mm diameter Klambon Steel rising main
  • Six Reinforced Concrete Reservoirs
  • Four Pump Stations
  • Access Roads to Pump Stations