Ncora Water Treatment Works

Project Details:

Project Description:
Cluster 4 Water Backlog: Ncora Scheme Bulk Pumping, Water Treatment Works and Reservoir

Contract No:
38/2011/MD (TN)

Category:
Municipal Infrastructure

Client:
Chris Hani District Municipality

Consultant:
Camdekon Engineers

Value:
R63.6M

Completed:
April 2015

Project Overview / Summary:

B 507

Contracts Manager:
DF Bickell

Construction Manager:
H Greyling

 

The work comprises the construction of:

  • Two pumping stations with pumps, motors and electrical controls pumping 60l/s each.
  • Pumping mains 350mm and 300mm diameter PVC-U and steel, 2.4km long.
  • A 5.2ml/day water treatment works including an earth balancing reservoir, chemical and administration buildings, 2x horizontal settlement tanks, steel gravity sand filters, 800m³ clear water reservoir, sludge lagoons and appurtenant works.
  • 4x staff houses
  • 1x 1800m³ RC reservoir